Lake Bonney 1 SA, Australia

Lake Bonney stage 1 commenced full commercial operation in March 2005 with a total installed capacity of 80.5MW and a net capacity factor of 30.3%. Lake Bonney stage 1 comprises 46 Vestas 1.75MW wind turbines. It is located on the Woakwine Range, about 2km from the eastern shore of Lake Bonney, near Millicent in South Australia.  Lake Bonney 1

Key Information

Funding

Australian dollar denominated limited recourse debt provided by a syndicate of banks

Revenue

assurance

All the electricity and renewable energy certificate outputs are sold under a single long term offtake contract with a term of 10 years1

Customers

Country Energy - the fourth largest electricity retailer in Australia and wholly-owned by the government of New South Wales, Australia

Operation

Operations and maintenance contract for five year1 term with Vestas

Land

Land leases typically with 30 year2 tenure and option to extend for two additional five year terms

Regulatory

regime

Australian MRET Scheme

Note:
1. from the start of operations: 2005