Woodlawn Wind Farm

  • Commercial operation date: October 2011
  • Original Equipment Manufacturer (OEM): Suzlon Energy
  • Wind turbines: 23 x Suzlon S88
  • Total installed capacity: 48.3 MW
  • Infigen sells the output of the Woodlawn wind farm on a merchant basis

The Woodlawn wind farm achieved practical completion on 17 October 2011.The Woodlawn wind farm is adjacent to Infigen Energy's operational Capital wind farm and the Capital East solar farm.

Woodlawn wind farm is Infigen's sixth Australian wind farm and was delivered on time and on budget. The final construction cost was $115 million partially funded by a $55 million project finance facility which is now fully drawn.

The Woodlawn wind farm provides enough renewable energy annually to power approximately 23,000 homes.

The project has created more than 150 direct jobs during construction and many more indirect jobs including the fabrication of towers, buildings, switchrooms and electrical equipment all within Australia. Infigen has provided on-site apprentices with valuable work experience and the wind farm has also benefited the local community through increased economic activity.

Compliance

View the Construction Compliance Report,following the first 6 months of construction, and theOperation Environmental Management Plan.

Incidents

In accordance with the requirements of our Environmental Protection Licences for the Woodlawn wind farm, and in the unlikely event of an incident, Infigen shall report pollution incidents immediately to the NSW EPA, NSW Ministry of Health, Fire and Rescue NSW, SafeWork NSW and the relevant local council.

‘Immediately’ has its ordinary dictionary meaning of promptly and without delay. The process for notification is provided in the process flowcharthere.

Please contact Infigen Energy if you have any questions via phone at 02 8031 9900 or by emailingcrep.complaints@infigenenergy.com.

In Pictures